BRADNER
OVERPASS

Steel Pipe Pile Foundations

Location
Abbotsford, BC
Client
Coquitlam Ridge Constructors
Project Period
2025–Present
Services
Foundation Piles
Stage 3 in progress Stages 1 and 2 completed

Project Overview

The Bradner Overpass forms part of the Highway 1 widening between Lefeuvre Road and Ross Road in Abbotsford. The project includes eastbound and westbound bridge structures, with foundation construction divided into stages.

Our Scope

Henry Foundation Drilling’s scope covers the supply and installation of permanent steel pipe piles at the east and west abutments.

The piling package includes field splicing and internal pile cleanouts, with separate mobilizations and equipment transfers between work areas.

METHODS & EQUIPMENT

Technical
Highlights

Permanent steel pipe pile foundations at the east and west abutments.

Foundation system
Open-ended steel pipe piles
Installation methods
Rotary drilling and diesel impact driving
Drilling rig
Bauer BG20H
Crawler crane
Kobelco CK1100G
Pile driving hammers
APE D50 & PILECO D62

Project Execution

Equipment transfers between abutments were a key part of the work. HFDI coordinated early-morning moves with the project team under the project’s traffic-control arrangements.

The crane was dismantled, transported and reassembled as operations shifted from the west work area to the east.

Overhead utilities and limited working space also influenced equipment positioning. The crew adjusted the site layout as activities shifted between pile installation, splicing and cleanouts.