GOLDEN EARS RAPID STATION
Project Overview & Collaborative Engineering
Henry Foundation Drilling Inc. (HFDI) successfully executed the specialized design-build shoring scope for the new Golden Ears Pump Station infrastructure project. Partnering closely with Isherwood Engineering, HFDI co-designed a highly cost-effective, heavy-duty shoring solution engineered to dual-function as a structural support and a high-efficiency water cut-off wall for the site.
Deep Foundation & Structural Shoring Specifications
To manage the complex geotechnical requirements and hydrologic conditions of the project, a robust system utilizing heavy sheet piles, structural steelwork, and ground anchors was selected.
Material Specifications: Heavy-duty steel sheet piles with lengths reaching up to 80 feet to ensure deep structural penetration and optimal water seepage control.
Specialized Equipment Mobilization: HFDI mobilized a high-capacity lattice crawler crane configured with 180 feet of boom, paired with a high-frequency vibro hammer for precise sheet pile driving.
Precision Driving Mechanics: To prevent friction locking and ensure the sheets would not bind deep in the ground, our crews utilized a robust, custom-engineered template frame system during a meticulous, staggered driving process.
Strategic Subcontracting: HFDI seamlessly self-performed the entire sheet pile installation and complex structural steelwork, while Southwest Contracting executed the anchor installation phase for the project.