River District Secant Pile Project
Secant Pile Foundation Drilling in South Vancouver’s River District
Henry Foundation Drilling Inc. (HFDI) successfully completed a complex, high-stakes geotechnical project in South Vancouver’s dynamic River District community. Operating under demanding geotechnical constraints, our team delivered industry-leading foundation solutions tailored to difficult urban waterfront conditions.
Project Overview & Technical Scope
Project Scale: Installation of 460 secant piles at 900mm diameter, reaching depths of up to 18 meters.
Site Challenges: Navigated difficult soil conditions coupled with a high water table located just 2 meters below the ground surface.
Advanced Drilling Fleet: Utilized heavy-duty Bauer equipment, including BG39, BG30, and BG28 drill rigs, alongside a 100-ton crawler crane dedicated to concrete placement.
Engineering Solutions for Complex Ground Conditions
The pile toes terminated in a clean sand layer, presenting a severe operational hurdle: extracting casings risked creating suction and disturbing the critical bearing stratum. To overcome this challenge and ensure long-term structural integrity:
Specialized Airlift System: HFDI deployed a specialized airlift system to successfully finish 330 of the 460 piles